ZweigWhite CE News Structural Engineer Rebuilding America's Infrastructure  
 
SEARCH  GO




New classical design in NYC’s Upper East Side

August 2009 » Exclusive

Archaeology and research allow Hage Engineering to secure an optimal structural system


By Mark Hage, P.E., William Doll, P.E., Richard Lee, P.E., S.E., LEED AP

Located near Central Park on the Upper East Side of New York City’s Carnegie Hill District, the Carhart Mansion is a landmark building completed in 1916. It was built for Marion Carhart, the widow of Amory Carhart, a banking and railroad magnate. The mansion set the trend for subsequent mansions built in the French Neo-Classical style in the neighborhood. However, Marion Carhart died before she could occupy her home. Designed by the architect Horace Trumbauer (1868-1938) as a one-family residence, the five-story gilded Parisian-style townhouse had been used up until 2001 by Lycée Français as a French grammar school. Immediately adjacent and to the east of the mansion, a two-story nondescript building, built in 1957, was used by Lycée for classrooms and a gymnasium.

Design and Construction Team

Structural engineer
Hage Engineering, P.C., New York

Design architect
Zivkovic and Associates P.C., New York

Contractor
F.J. Sciame Construction Co., Inc., New York

Geotechnical engineer
Pillori Associates, P. A., Laurence Harbor, N.J.

Mechanical engineer
Charles G Michael Engineering, P.C., White Plains, N.Y.

Hage Engineering’s project team
Mark Hage, principal, structural engineer of record; Richard Lee, senior associate, project manager; William Doll, associate, project engineer; Andrew Cilley, engineer; Tommy Taveras, engineer; and Mimi Lischin, engineer

In 2001, the school sold both properties to a developer who planned to renovate the mansion, demolish the two-story structure, and erect a new building in its place, thus creating a single luxury condominium on the two sites. Our firm, Hage Engineering, was engaged to provide the structural design. The architectural firm Zivkovic Associates was hired to design the project. Zivkovic’s design proposed a six-story residential replacement building that would seamlessly connect to the mansion. The British architect John Simpson partnered with Zivkovic Associates and advised on the classical elements of the new façade. Sciame Construction Company was selected as the general contractor. The design was accepted and approved by the city and the Landmarks Commission and was deemed complimentary to the adjacent buildings and neighborhood.

The existing 32,000-square-foot mansion contained double-story floors — which were tall enough to allow for the insertion of new floors — that originally were used for ballrooms and dining rooms. A large marble curving staircase within the lobby was preserved, and a penthouse covering a portion of the roof was enlarged. The new building would add 17,000 square feet and boast a private garden in the rear, a new service elevator, a penthouse with an outdoor terrace, and a rooftop lap pool.

Mansion renovation
The structural system for the mansion consisted of steel beams and girders that bore on solid multi-wythe brick load-bearing walls around the perimeter, supported by steel and cast iron columns at the interior bays. The floors were constructed by formed cinder slabs (flat arches) that spanned between the steel beams, which are spaced roughly 5 to 6 feet-on-center. The cinder slabs were reinforced by draped wire mesh continuous over the top flanges of the beams and hooked at discontinuous ends. At the time, this type of construction was slowly supplanting the popular terra cotta arch systems for a dominant market share of fireproof floor construction in New York City.

To create new floor levels and new penetrations, steel framing was erected with new composite metal deck concrete slabs. Testing on the existing steel was performed to determine the grade and weldability of the steel, which was determined to be weldable. The design team was assisted by the original structural drawings and steel shop drawings that were buried within New York City’s archives and uncovered by the Office of Metropolitan History. An inordinate amount of floor probes would have been needed to determine the original building framing without the benefit of the original drawings.

Part of the mansion’s renovation included new steel framed floors with lightweight concrete topping over varying depths of composite metal decks. These slabs were inserted between existing floors to create duplexes and were used for the enlargement of the existing penthouse. Because of the additional lateral loads, the existing steel framing at the penthouse was analyzed and upgraded by reinforcing the existing connections and girders.

Since the façade of the building is landmarked, the team decided to address the deterioration in the masonry and to restore it to its original appearance. The walls consisted of multi-wythe brick with limestone cladding on the exterior. For the most part, the backup brick walls were in good condition with only minor repointing and rebricking required. The bulk of the work consisted of removing and resetting limestone pieces that were cracked or broken. Lastly, the building’s façade was power-cleaned to its original appearance.

Existing steel beam and girder connections to existing cast iron column were all tested for grade and weldability.
A cast-in-place, full-height concrete wall proved to be the best solution for the new building’s front wall (shown here with concrete formwork in place during construction).
the existing two-story building was demolished, but the existing foundation walls (on the right in the photo) remained as a temporary soil retention system.

New building
Geotechnical investigations at the site revealed a water table and poor soils close to the elevation of the new basement level. Soil borings also revealed bedrock at approximately 30 feet below that elevation. In order to limit dewatering and reach the required rock bearing level, the geotechnical engineers at Pillori Associates recommended a deep foundation system consisting of drilled, 120-ton, mini-caissons filled with high-strength grout. The caissons’ actual capacity was later value engineered by Sciame Construction to a higher capacity, which allowed for the use of one caisson below certain columns. The mini-caissons were socketed into the bedrock and braced with reinforced concrete pile caps and grade beams.

Since a large excavation was being undertaken, a soil retention system was contemplated in order to maintain the stability of the adjacent landmarked Fabbri Mansion and its plaza. Rather than installing a new soil sheeting and bracing system, the team decided to keep the existing foundation walls from the demolished, two-story gymnasium and use them as part of a temporary soil sheeting and shoring system. These walls were braced into the interior area of the excavation until new abutting foundation walls were built. The new foundation walls were placed inboard of the extant walls and were designed to retain the soil load on a permanent basis. Since the new foundation walls were set back from the new walls above, large concrete beams were designed at the first floor to cantilever over the old foundation walls and to support the new facades for the full height of the building.

Another challenge for the team was aligning the new floor plates with the existing elevations at the mansion. Based upon conceptual analysis of various floor assembly systems, a two-way reinforced concrete slab floor system was chosen. With a total assembly thickness of only 9 inches, this slab offered the most flexible system and allowed for ductwork and finishes to align with the existing floors and provide the needed head height for a New York City luxury apartment. A steel system was explored and rejected because the floor assembly was too deep.

The concrete slabs spanned between the concrete columns and concrete walls at the elevator core. In order to limit deep transfer beams, each floor layout was re-examined and modified to align columns at the same location on each floor. This allowed the contractor to use the same formwork at multiple levels. However, at the penthouse, where architectural layouts could not be adjusted, single-story height concrete columns were transferred onto columns below by composite concrete and steel beams. This maximized needed head height and minimized long-term deflection. At the new penthouse roof, concrete beams were incorporated to support a future rooftop lap pool.

The façade design for the three new exposed sides of the new building called out for stone veneer. Concrete spandrel beams with reinforced CMU backup walls were initially explored. After reviewing the window penetration geometry, engineers determined that only minimal areas of the wall would require CMU backup. In order to eliminate steel lintels and awkward CMU construction, the front and rear backup walls were constructed of reinforced concrete with punch-outs within the formwork to allow for windows.

These full-height concrete walls at the front and rear of the building were used as shear walls to resist the wind and seismic lateral forces. To resist the lateral forces in the perpendicular direction, the full height of concrete walls around the stair and elevator core were used as shear walls. The original building was built prior to the New York City’s seismic code enactment. Therefore, at the beginning of the design process, the design team decided that the new building would not be attached to the original building. Had the two buildings been connected, the original building’s unreinforced masonry walls and footings would have needed reinforcement. To accommodate this separation, a seismic joint was placed between the new and old buildings.

To maintain the schedule, the shear walls were poured prior to determining the location of some of the mechanical openings that were required at the stair walls. Once those openings were located, a new analysis was performed on the shear walls. To reinforce the new openings, new reinforcing steel plates were added at the perimeter of the openings, where needed.

Summary
The project received the Palladio Award for classical architecture in 2006. The restored mansion and the new building combined to create a seamless contextually respectful addition to the neighborhood. A thorough understanding of the archeology of turn-of-the-century structural systems and diligent initial research into as-built conditions allowed for selections of optimal systems. This focused approach at an early stage of determining the unique issues relating to a hybrid urban building allowed for sound conceptual selections that resulted in a construction phase that met the projected timelines.

By the numbers: 3 East 95th Street

Physical size and shape of project

Number of square feet: 49,000            Number of stories: 8

Structural system types:

  • Renovation: Metal deck concrete slab spanning between existing interior steel beams; multi-wythe brick load bearing walls around perimeter
  • New Building: Two-way reinforced concrete slab with concrete spandrel beams with concrete shear wall and concrete frame for a lateral system

Foundation type: drilled mini-caissons

Unique project aspects

  • Because of the varied geometry of the façade openings, the front and rear backup walls for the new building were built entirely out of cast-in-place concrete.
  • Composite concrete and steel beams were used at concrete column transfers at the upper portions of the new building and minimize long-term deflection.
  • New masonry veneer elements were designed to conceal the seismic joint between the new and the existing building.
  • Single mini-caissons with a high capacity were used to support the new columns and foundations. Concrete grade beams in the two major directions were designed to brace these pile caps.
  • Used original structural and steel shop drawings from New York City archives for renovation design.

Construction materials — amounts

Total tons of structural steel: 46           Tons of rebar: 65

Cubic yards of concrete: 1,100           Square feet of deck: 9,650

Number of footings: 5 interior footings at the existing building

Number of piles: 28 piles at the new building

Unique construction aspects

  • A 54-inch-wide concrete column was used to transfer offsetting columns.
  • Two built-up 24–inch-deep steel beams were uncovered at the existing building supporting a masonry wall.
  • The roof slab at the new building was designed to support a lap pool.

Project schedule

Timeframe for design completion: 6 months

Timeframe for construction completion: 18 months

Key products

  • Styrofoam Brand Plazamate, from Dow Building Solutions, was used as a roof top pitched insulation in place of excessive concrete fill.
  • Epoxy anchor bolts from Hilti were used at concrete and masonry substrates.
  • Bentley’s STAAD modeling software was used for design of some steel frames.
  • StructurePoint’s spSlab (formerly called PCA ADOSS) for concrete analysis and design.
  • Enercalc, from Enercalc, Inc., was used for foundation and steel framing design.

Firm facts: Hage Engineering, P.C.

Firm leader: Mark Hage, P.E., principal

Headquarters: New York City

Year firm established: 1990

Number of employees: 11

Areas of practice: renovations and rehabilitations, new construction, high-rise and special structures, façade restoration for structural work, historic structures, industrial and artwork design, forensic engineering, structural investigations, and analysis for sustainability upgrades.

Markets served: residential, public, commercial, educational, and industrial.

Firm awards: The Preservation League of New York State “Excellence in Historic Preservation,” 2009; Rank #1 in Structural Engineer’s 2008 Best Structural Engineering Firms To Work For; Sara National Design Award of Excellence, 2008.


Q&A with the SE

Structural Engineer Editor Jennifer Goupil, P.E. (JG), interviewed Associate William Doll, P.E. (WD), of Hage Engineering, P.C., regarding the structural challenges of the renovation and new construction at 3 East 95th Street in New York.

JG: What was the first task you needed to do to get started on the design?

WD: For the existing building, the first task was investigating the existing structural system. For the new building, the first task was evaluating several structural systems in terms of cost and coordination with the architect’s requirements, and value engineering the various schemes.

JG: What types and how many structural systems did you and your team evaluate for this project?

WD: We evaluated several: a rigid steel moment frame, a braced steel frame, steel framed floors supported by masonry bearing walls, and a concrete framed building.

JG: How did you select the final structural system?

WD: Based on preliminary cost estimates, the concrete frame proved to be the most expensive. However, the concrete system was selected based on speed of construction [it could be built the fastest] and because it was the best solution for the architect’s requirements.

JG: What was the most challenging aspect of the structural design?

WD: [The challenge was] designing a new building and [delivering] structural members within an urban, constricted area with adjacent properties that needed to keep functioning.

JG: What was the most unique problem to solve on the project?

WD: [Unique to this project was] designing the new foundation walls while not undermining the existing neighbor’s courtyard and sidewalk. The design team decided to maintain the existing foundations wall as a temporary soil retention system until the new foundation walls were erected. The new façade was supported by slab and beams cantilevered over the new foundation walls.

JG: Were there any surprises? How did you adapt to them?

WD: [Two in particular], the high water table did not allow for the shallow spread footings, so we used mini-caissons as a deep foundations system to avoid the water table. [Also, several] openings in the shear walls at the stairs were cut and reinforced for the installation and maintenance of the mechanical ducts and pipes after the wall was built.

JG: What lessons did you learn from this project?

WD: Since space between existing buildings in New York City are usually tight, by using existing elements of the foundation system as a temporary soil retention system until the final system was installed ensured that we would not disturb the neighbors.

JG: What engineering ideas did you implement to save project costs?

WD: The deep foundation system for the new building helped save money on dewatering.

And, by using the existing foundation walls as a temporary soil retention system meant that the general contactor didn’t have to spend money on a new temporary soil retention system. We also used medium-high strength concrete to reduce slab deflection and concrete member sizes. [And, another benefit of the] front and rear concrete shear walls was that they [eliminated the need for] the CMU and steel lintel trades [from that component].

JG: Do you have any other comments regarding the structural challenges of this project?

WD: This project essentially consisted of designing two separate buildings: one was a steel building renovation and the other was a new concrete building. The overall challenge was balancing both designs and producing drawings for both at the same time. [The most interesting part, for me, was] dissecting how the existing building was put together and then coordinating the new design with the existing building.

Principal Mark Hage, P.E., Associate William Doll, P.E., and Senior Associate Richard Lee, P.E., S.E., LEED AP, are all with Hage Engineering, which was founded in 1990. They can be reached at 212-358-7778 or via e-mail at mhage@hageengineering.com, wdoll@hageengineering.com, and rlee@hageengineering.com, respectively.

 
Related Engineering Channels




Headlines From Around The Web







Current Issue

cover May 2012

» Cover Story
A brighter outlook

» Features
Products and services

All articles     eZine    Subscribe

Cover Story

A brighter outlook

After years of ups and downs, cautious optimism greeted 2012. While economic progress lagged in 2011, this year started off with most in the consulting engineering industry adjusting and rising to the challenges of a volatile economy.


News


New & Noteworthy


Places & Faces


From The Publisher


Comments



Events